javascript
---------------- Javascript Base ----------------
bootstrap5 - SET
bootstrap5 - SET
---------------- Javascript Base ----------------
main
navigation
ShiftBulk
wrassepinnedissue


javascript_special
---------------- Javascript Special Requirements ----------------
handlebars
alpaca
highcharts
cropper
mathjs
jsoneditor
leaflet
---------------- Javascript Special Requirements ----------------
modification_btn
docs

messages
shoppingcart
datatablesearch

Navigation
docs_nav



flatprojectmap.handlebars
General Inclusions and Exclusions
modificationbutton
59100a40d0c87d43a495141b
docs_htmltables.handlebars

This table provides a list of contract inclusions that should be reviewed for a bulk material handling project .This table of items could be considered a check list of key project considerations, before , during and on completion of a bulk materials handling project.


docs_datatable.handlebars
General Inclusions and Exclusions
Belt rip protection systems
Operational spares
Compressed Air
All transportation of conveyor equipment on site.
Centralized lubrication
Area lighting, high mast lighting etc.
Conveyors at river crossings are fully enclosed.
Transfer points are enclosed and fitted with dust suppression systems to minimise dust pollution.
Belt magnets for tramp metal removal.
All equipment safety signage.
Belt scales.
Spares holding optimization
All area separation , including vehicle gates, pedestrian gates , fences etc.
Interlocking Industrial Paving
Conveyors are fitted with HDPE idlers to minimize noise.
Surface conveyors without dog housing to have hold down points for wind on the head and tail frame.
Drainage
LV lighting and small power transformers
Trenching
Conveyor motor cabling and mini substations mounted on skid frames.
All civil work precast fabrication required for the installation of the conveyor.
Modifications to Existing Site
Variable speed drives
Surface runoff at transfer points are locally contained by means of bund walls linked to silt traps. Silt traps with drying pads are provided at all transfer points.
Dust suppression
Power conditioning and power factor correction equipment
Integration to higher level PLC and SCADA systems
Access and haul roads
Corrosion protection and touch up paint.
Compliance with site safety and environmental training requirements prior to commencing work, personnel medical and safety inductions.
Fiber optic or copper cable to PLC / SCADA system
Detailed conveyor structural loadings and bolt loadings.
Rationalization for drives , gearboxes , pulleys , belting or idlers.
First fill of lubricants.
Fire hydrants or fire extinguishers .
Lighting on conveyors and in transfer stations
Electrical work other than on-board conveyor electrical equipment
All civil work installation required for the installation of the equipment.
No transfer points, loading points or discharge points are located within wetlands.
Potable water.
Geotechnical survey and site survey
HAZOP studies and resultant design changes.
Clearing of construction area of all debris, material , existing steelwork , civils etc. To allow for all new construction work.
Mechanical and structural engineering design and drafting
Transformers
Testing and commissioning of the equipment.
All splicing , joining and repair of belting.
Spillage handling
All civil work design required for the installation of the equipment.
Procurement of equipment, spares and sub-contactors
For service roads across wetland areas, culverts will be placed at regular intervals (maximum spacing of approximately 50 m) to allow the through flow of surface runoff.
Conveyor dynamics analysis
Packing, marking and transport of all material and equipment to site.
An overall width of 8 m for single conveyors and 20 m for dual conveyors has been allowed for. This makes provision for the conveyors and associated service roads. The service roads will have gravel surfacing. The conveyors have generally been located above the natural ground level (i.e. on fill) and along the alignment of existing roads, where possible.
Relocation of Existing Services
Material flow testing
Diversion of roads, haul roads, pipelines, rivers etc.
Water management, process water, sewage etc.
Civil work including clearing, earthworks, design and grouting
Motor control center or programming of MCC components
All underground flame proof equipment.
Fire detection and/or suppression systems.Gantries elevated more than 7m should make an allowance for fire suppression at the head end of the conveyor. Water bowsers to be used for fire suppression on the ground level.
Site Surveying
Any blasting, cutting or trimming of underground rock or coal.
Supply of all fasteners, gaskets, packers, shims, masonry anchors and loose fittings as required to do the installation of the works.
Mobilization of all supervision, labour, materials, power supply, tools, construction plant and equipment, transport necessary for completion of the work.
Considerations are to be made for conveyors crossing wetlands.
Site Security and equipment lock-up.
Underground personal safety devices ( Lamp , emergency rescue pack and battery pack )
All lifting and rigging equipment.
Personnel protective equipment
Toilets
Communications Underground
Washing down of area to clear spillage.
Considerations for the support of the mass of conveyor drives during maintenance on the low speed coupling.
Belt snapping at the highest point of tension and risk for the inclined conveyor feeding the silo which may result in potential structural damages which requires the inclusion of belt arrestors with run back idlers
A risk of water collecting on the belt – belt slipping is eminent and require that the design must make sure that water can run off from all the belt's tail pulleys
Fire booster water truck points.
Programmable Logic Controller (PLC) and SCADA software development
All drawings and documents available will be made available in native format and only minor changes to these documents and drawings will be necessary to finalise the design
No allowance is made to changes to the current concept design. The contractor does not necessarily agree with the concept.The impact of such a change can only be verified after the re-design and selection of the updated concept design.
No time allowed for Environmental Services
Costs related to vendor/contractor visits and assessments (including Quality teams)
Structural Steel Detailing
The standard drawings produced by the FEL3(BFS) contractor are acceptable and can be used without significant modification by the successful FEL4 contractor.
Hydro-geological or mine exploratory geotechnical investigations
Any time for As Built drawings , or offsite support for construction managamenet.
Any negotiations with Eskom or Transet.
All site rigging points, including working at heights rigging locations and lifting points for mechanical and electrical equipment maintenance.
Substation airconditioning design , UPS for AC and redundancy requirements.
Some coal tipper trucks make use of auto-tarpaulin closing systems, these systems have larger clearance heights. Designs for loading equipment to cater for these additional clearance heights.


searchflatarrary.handlebars


wrasseform.handlebars

childType : 59100a0cd0c87d43a4951418
elementID : 59100a40d0c87d43a495141b
modal1
modal2
modal3
docs_javascript

shortcut_edit

ShiftBulk

A platform developed to streamline conveyor system design, procurement, and maintenance in mining operations. Beta 1.0.0

Built with the Fraternate user framework

Sign up to get started!

Sign up

Site Details
Issues
Terms and Conditions
Collaborate

If you are interested in collaborating on an activity or project, we welcome you to reach out to us.

footer
© 2024 ShiftBulk